WATER & ENVIRONMENT

Karun River

Dredging studies, river improvement, bank protection and supervision across different reaches of the Karun.

River EngineeringArea of expertise
Studies & SupervisionAssignment types

Dredging Studies & Supervision

Assignments include dredging studies for the Farsiat reach and the Chanibieh–Moran reach, studies downstream of Ahvaz, supervision between the Fifth Bridge and Lower Chanibieh, and third-stage engineering services for dredging at Khorramshahr.

River Improvement & Bank Protection

Other assignments address navigation feasibility, river improvement for water transport, erosion control near a treatment plant and bank protection around material-extraction pits near Gotvand.

Assignments by Reach

مطالعات فاز 2 لایروبی کارون بازه فارسیات

Assignment reference: WE054

انجام بخشي از خدمات مطالعات و طراحي مرحله دوم عمليات لايروبي كارون بازه چنيبيه تا موران

Assignment reference: WE064

پروژه كنترل فرسايش جانبي رودخانه كارون در محل تصفيه خانه

Assignment reference: WE070

پروژه مطالعات مرحله اول ساماندهی رودخانه كارون با هدف ترابري آبي

Assignment reference: WE080

پروژه امكان سنجي كشتيراني در رودخانه كارون

Assignment reference: WE092

پروژه مطالعات و تهيه طرح ساماندهي گودالهاي برداشت مصالح و حفاظت سواحل رودخانه كارون_ گتوند

Assignment reference: WE114

پروژه طرح ساماندهي گودال هاي برداشت مصالح و حفاظت سواحل كارون در پايين دست سد گتوند

Assignment reference: WE117

پروژه مطالعات بخشي از فاز 2 عمليات لايروبي آبراه كارون به منظور كاناليزه كردن و افزايش ظرفيت آبگذاري در پايين دست شهر اهواز

Assignment reference: WE139

پروژه عمليات لايروبي رودخانه كارون بازه پل پنجم تا چنيبيه سفلي

Assignment reference: WE143

پروژه نظارت بر اجرای ساماندهی رودخانه کارون

Assignment reference: WE175

پروژه خدمات مهندسی مرحله سوم لایروبی رودخانه کارون در خرمشهر

Assignment reference: WE202

کارفرما: سازمان آب و برق خوزستان

نظارت رودخانه کارون در محدوده پل پنجم تا پارک شقایق

Assignment reference: WE215